Kinepolis Theater Complex Breda - Designed with BIM Studiebureau Boydens

description

In the commercial area in the city of Breda, a new cinema complex with 10 theater halls accommodating a total of 1.727 seating and a full-fledged B2B event hall has been constructed. To safe guard the environmental impact of the building, the project is designed on pillars in order to create sufficient place for parking and landscape.
The building is  designed according to the highest standards of energy efficiency and environmental legislation.
Air handling units with heat recuperation, state of the art controls and building management systems, heating and cooling production with high efficient condensation boilers and pumps.

2138

general data

total cost price: ± € 15.750.000,00 hors TVA

total area: 6.780 m²

Study start date:: October 2014

completion date: July 2016

nature of work: Construction: study and following up MEP

cost techniques: ± € 2.500.000,00 vat excluded

client

Kinepolis Group nv, Schelde I, Moutstraat 132 - 146, 9000 Ghent, BE

architect

Van Overbeek & Partners, Nieuwe Prinsenkade 4-A , 4811 VC Breda, NL